(As a matter of size limit, those projects mentioned herein just provide general information on background of and bases for the setup thereof. Other related contents, e.g. SWOT Analysis, Business Plan, Marketing Plan, Revenue Forecast, Financial Forecast, etc…will not be presented).

 

Overview

Prominent feature of the economic and social development of Dongnai province is the appearance and development of concentrated industrial parks. The master planning of 17 industrial parks of Dong Nai covering totally 8,119 hectares has been determined. The industrial park infrastructure has been invested in by seven enterprises, two of which are foreign investors. Total investment capital for the infrastructure construction is USD 62 million. At present, the infrastructure of more than 5 industrial parks has fully constructed, including Bien Hoa 2, Amata, Loteco, Nhon Trach and Go Dau industrial parks.


Current industrial parks in Dongnai province:

Bien Hoa 1 Industrial Park

Bien Hoa 2 Industrial Park
Amata Industrial Park
Loteco Industrial Park
Song May Industrial Park
Ho Nai Industrial Park
Go Dau Industrial Park
Ong Keo Industrial Park
Nhon Trach Industrial Estates, including :

- Nhon Trach 1 Industrial Park: 448 ha

- Nhon Trach 2 Industrial Park: 700 ha
- Nhon Trach 3 Industrial Park: 350 ha
- Nhon Trach 4 Industrial Park: 350 ha
- Nhon Trach 5 Industrial Park: 556 ha, for first phase: 300 ha.
- Nhon Trach 6 Industrial Park: 616 ha, for second phase: 100 ha.

 

DEMAND AND MARKET TARGETED UNDER THE PROJECT

The foundation and development of a series of industrial parks in Dongnai province to meet the province's targets of economic and social development did create great demands on transport and portage services in view of a great amount of goods and products moving in and out of these industrial parks. In this scenario, the project involving a container freight station in Long Tan commune, Nhon Trach district appears to fit the gap. The market of this project targets on the volume of goods and products moving to and from industrial parks in Dongnai province and other ports in Ho Chi Minh city …

Project implementation schedule :

Compensation and removal of households : 1 st month – 3 rd month.
Ground filling : 4 th month – 5 th month.
Construction of internal roads, yards (including goods storage area): 6 th month 6 – 7 th month.
Construction of outside roads: 6 th month – 9 th month.
Construction of 2 jetties : 6 th month – 7 th month.
Construction of office building: 7 th month – 8 th month.
Construction of warehouses: 8 th month – 9 th month.

Total time span of these construction works might be 9 months. It is estimated that withnin the tenth month they would be finally verified for acceptance and put into operation.

Add : 96 National Highway, Quyet Thang Ward - Bien Hoa City- Dong Nai Province - Viet Nam
Tel: (84-61) 822 486 - Fax : (84-61) 823747 - 829467 - E-mail : info@timexco.com.vn
©Copyright 2005 TIMEXCO